Placing concrete, lorry based pump |
30.0 |
40.0 |
50.0 |
m3/hr |
Hollorib Decking, concrete topping |
85.0 |
100.0 |
120.0 |
m2/hr |
Hollorib Decking, concrete topping, incl PowerFloat |
40.0 |
50.0 |
70.0 |
m2/hr |
Placing Concrete, By Wheelbarrow over 1-10m |
2.1 |
2.3 |
2.5 |
m3/hr |
Placing Concrete, By Wheelbarrow over 10-20m |
1.5 |
1.8 |
2.1 |
m3/hr |
Placing Concrete, By Wheelbarrow over 20-50m |
0.8 |
1.1 |
1.5 |
m3/hr |
Placing Direct From Readymix Lorry, Mass Fill |
2.8 |
3.1 |
3.3 |
m3/hr |
Placing Direct From Readymix Lorry, 50mm Blinding |
- |
1.3 |
1.6 |
m3/hr |
Placing Direct From Readymix Lorry, Ground Beams |
1.5 |
- |
1.7 |
m3/hr |
Placing Direct From Readymix Lorry, Pile Caps |
1.0 |
1.5 |
2.3 |
m3/hr |
Placing Direct From Readymix Lorry, Duct Walls |
- |
0.8 |
1.1 |
m3/hr |
Placing Direct From Readymix Lorry, Stub Columns |
- |
0.4 |
0.6 |
m3/hr |
Placing Direct From Readymix Lorry, Ground Slab |
2.1 |
2.3 |
2.6 |
m3/hr |
Placing Direct From Readymix Lorry,Drains Bed and Cover |
- |
0.9 |
1.0 |
m3/hr |
Placing From Tower Crane, Pile Caps |
1.2 |
1.4 |
1.6 |
m3/hr |
Placing From Tower Crane, Mass Fill |
4.0 |
4.5 |
5.5 |
m3/hr |
Placing From Tower Crane, Slabs under 150mm thick |
0.9 |
1.3 |
1.7 |
m3/hr |
Placing From Tower Crane, Slabs over 150mm thick |
1.2 |
1.5 |
1.8 |
m3/hr |
Placing From Tower Crane, Trough/Coffered Slabs |
0.9 |
1.1 |
1.2 |
m3/hr |
Placing From Tower Crane, Stairs and Landings |
0.6 |
0.7 |
0.9 |
m3/hr |
Placing From Tower Crane, Blinding |
0.8 |
1.0 |
1.1 |
m3/hr |
Placing From Tower Crane, Beams under 150mm thick |
0.5 |
0.6 |
0.8 |
m3/hr |
Placing From Tower Crane, Beams over 150mm thick |
0.6 |
0.8 |
1.0 |
m3/hr |
Placing From Tower Crane, Walls |
0.6 |
1.1 |
1.5 |
m3/hr |
Placing From Tower Crane, Columns |
0.4 |
0.5 |
0.6 |
m3/hr |