FST Floating Track Slab, side restraints |
9.6 |
- |
- |
m/day |
FST Floating Track Slab, resin pads |
10.2 |
- |
- |
m/day |
FST Floating Track Slab, slab units |
10.6 |
- |
- |
m/day |
PCBT - Pre-cast Concrete Block Track, in Bored Tunnels |
17.1 |
41.0 |
- |
m/day |
PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels |
- |
35.0 |
- |
m/day |
PCBT - Pre-cast Concrete Block Track, in Station Tunnels |
- |
35.0 |
- |
m/day |
IST - Isolated Slab Track, in Bored Tunnels |
- |
20.0 |
- |
m/day |
IST - Isolated Slab Track, in Cut and Cover Tunnels |
- |
34.0 |
- |
m/day |
IST - Isolated Slab Track, in Station |
- |
29.0 |
- |
m/day |
FST - Floating Slab Track, in Station |
3.6 |
4.6 |
5.7 |
m/day |
Ballasted Track, in Mainline |
57.0 |
71.0 |
115.0 |
m/day |
Ballasted Track, in Depot |
- |
28.0 |
- |
m/day |
Non-Ballasted Track, in Depot |
8.5 |
12.8 |
17.4 |
m/day |
Embedded / Paved Track, in Depot |
- |
71.0 |
- |
m/day |
Heavy Maintenance / Train Wash Track, in Depot |
- |
29.0 |
- |
m/day |
Maintenance Pit, in Depot |
- |
52.0 |
- |
m/day |
Siding Trackwork, in Depot |
- |
38.0 |
- |
m/day |