AC Install 2 no Service transformers, 6 men |
- |
12.0 |
- |
days |
AC Install 2 no Switchgear, 7 men |
- |
12.0 |
- |
days |
AC Install Associated Trays and ladders, 3 men |
11.0 |
5.0 |
- |
days |
AC Cable Terminations in Tx and SWG Rooms, 3 men |
12.0 |
6.0 |
- |
days |
DC Install Insulated Flooring in DC Room, 1 men |
- |
5.0 |
- |
days |
DC Install 1 set Rectifier Transformer and Rectifier, 7 men |
- |
1.0 |
- |
days |
DC Install Switchgear, 7 men |
- |
10.0 |
- |
days |
DC Primary Cable Terminations and Busduct, 18 men |
12.0 |
9.0 |
- |
days |
DC Secondary Cable Terminations and Connections, 9 men |
12.0 |
6.0 |
- |
days |
Trackside Cabling 33kV/Pilot Cables, 10 men |
2,100.0 |
- |
- |
m run/day |
Trackside Cabling Terminations, 6 men |
- |
1.0 |
- |
days |