- Category: Cable
- Hits: 15934
Construction Man-hour Norms
Description | Constants include drawing cabling in sets of four cables plus | Unit | Tradesman Hours | Labourer Hours |
Cable | ||||
approved size earth cable into adequately sized conduits, with | ||||
minimal long sweep bends, and for fixing cabling to top of | ||||
horizontal single side supported trays. | ||||
TPI cable in conduit | ||||
2.5mm2 | m | 0.03 | ||
6mm2 | m | 0.04 | ||
25mm2 | m | 0.05 | ||
35mm2 | m | 0.06 | ||
95mm2 | m | 0.09 | ||
Four core and earth PVC/PVC circular cable on tray | ||||
2.5mm2 | m | 0.08 | ||
6mm2 | m | 0.11 | ||
16mm2 | m | 0.17 | ||
35mm2 | m | 0.23 | ||
95mm2 | m | 0.42 | ||
150mm2 | m | 0.59 | ||
MIMS/PVC cable on tray, single core | ||||
6mm2 | m | 0.11 | ||
10mm2 | m | 0.13 | ||
25mm2 | m | 0.17 | ||
50mm2 | m | 0.23 | ||
70mm2 | m | 0.25 | ||
120mm2 | m | 0.32 | ||
MIMS/PVC cable on tray, four core | ||||
4mm2 | m | 0.11 | ||
6mm2 | m | 0.13 | ||
10mm2 | m | 0.17 | ||
16mm2 | m | 0.23 | ||
25mm2 | m | 0.25 |
- Category: Cable
- Hits: 19164
Planning and Estimating Production Rates
Task / Description | Slow | Ave | Fast | Units |
Cable Installation, 1 cable laid in trench and protect | - | 6.2 | - | m/hr |
Cable Installation, 2 cable laid in trench and protect | - | 5.6 | - | m/hr |
Cable Installation, 5 cable laid in trench and protect | - | 4.3 | - | m/hr |
Cable Installation, 7 cable laid in trench and protect | - | 3.7 | - | m/hr |
Cable Installation, 8 cable laid in trench and protect | - | 3.5 | - | m/hr |
Cable Installation, 2 cable laid in trench and protect, 100mm dia | - | 1.8 | - | m/hr |
Cable Installation, 2 cable laid in trench and protect, 135mm dia | - | 1.6 | - | m/hr |
Cable Installation, 3 cable laid in trench and protect, 100mm dia | - | 1.0 | 1.5 | m/hr |
Cable Installation, 6 cable laid in trench and protect, 100mm dia | - | 0.7 | 1.2 | m/hr |
Cable Installation, 4 cable laid in trench and protect, 150mm dia | 0.7 | 1.2 | 3.1 | m/hr |
Cable Installation, 36 cable laid in trench and protect, 100mm dia | - | 0.2 | - | m/hr |
Cable Installation, 10 cable laid in trench and protect, 100mm dia | - | 0.5 | - | m/hr |
Cable Installation, 1 cable laid in trench and protect, 300mm dia | - | 1.3 | - | m/hr |