- Category: Conduit
- Hits: 15381
Construction Man-hour Norms
Description | Tasks | Unit | Tradesman Hours | Labourer Hours |
Conduit | ||||
Constants include installing a nominal quantity of bends | ||||
and conduit fittings and saddling, to comply with wiring | ||||
regulations where required. | ||||
UPVC Conduit | ||||
Fixed to masonry maximum 4m above floor | ||||
20mm diameter | m | 0.15 | ||
32mm diameter | m | 0.18 | ||
50mm diameter | m | 0.22 | ||
Cast into suspended concrete slab | ||||
20mm diameter | m | 0.05 | ||
32mm diameter | m | 0.06 | ||
50mm diameter | m | 0.08 | ||
Fixed within suspended ceiling space | ||||
20mm diameter | m | 0.11 | ||
32mm diameter | m | 0.12 | ||
50mm diameter | m | 0.15 |