Fix 0.5m2 Stones to Metal Support Frame |
5.6 |
7.0 |
7.8 |
m2/day |
Fix 0.5-0.75m2 Stones to Metal Support Frame |
7.2 |
9.0 |
10.1 |
m2/day |
Fix 0.75-1.0m2 Stones to Metal Support Frame |
6.9 |
8.7 |
9.7 |
m2/day |
Fix Complex Stonework to Metal Support Frame |
- |
1.8 |
- |
m2/day |
Fix Curved Stone Cladding |
6.9 |
8.0 |
9.2 |
m2/day |
Fix Stone Edge Beams/Window Reveals |
- |
2.3 |
3.2 |
m2/day |
Fix Stone Soffits |
- |
4.0 |
- |
m2/day |
Stone Floors |
6.9 |
10.4 |
12.2 |
m2/day |
Granite Wall Panels, First Fix |
- |
1.3 |
- |
m2/hr |
Granite Wall Panels, Second Fix |
- |
1.1 |
- |
m2/hr |