Planning and Estimating Production Rates
Task / Description | Slow | Ave | Fast | Units |
Overall Installation for 100 persons or 50m2 | - | 3.0 | - | wks |
Overall Installation for 500 persons or 150m2 | - | 5.0 | - | wks |
Overall Installation for 1000 persons or 250m2 | - | 8.0 | - | wks |
Install Ovens, friers and large mixers etc | - | 1.0 | - | mandays |
Install Sinks, bain maries and washers etc | - | 2.0 | - | mandays |